Multiple Choice
A _____ visually displays the tasks and times associated with a project and consists of a horizontal bar chart with activities listed vertically and times or dates displayed horizontally.
A) PERT tool
B) Gantt chart
C) CPM tool
D) TCO chart
E) networking tool
Correct Answer:

Verified