    In a PERT Network, A/an _____ Is the Earliest Point
Solved

In a PERT Network, A/an _____ Is the Earliest Point

Question 53

Question 53

Multiple Choice

In a PERT network, a/an _____ is the earliest point in time an activity can begin.


A) late start
B) on time start
C) early finish
D) early start
E) late finish

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q48: _ is a tool that reduces processes

Q49: By identifying unnecessary steps and resources, value

Q50: Activities without any slack in a PERT

Q51: A _ is one in which the

Q52: According to Ohno and Toyota, _ is

Q54: When a process crosses functional boundaries, there

Q55: According to Ohno and Toyota, _ is

Q56: Which of the following is not one

Q57: If learning occurs at a supplier during

Q58: Users apply _ to projects where there

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines