Multiple Choice
Which of the following is not one of the network rules for PERT/CPM?
A) Networks can start and finish at multiple events.
B) Identify each unique activity within a project by a capital letter that corresponds only to that activity.
C) Branch direction indicates the general progression in time from left to right.
D) When a number of activities end at one event, no activity starting at that event may begin before all activities ending at that event are complete.
E) Two or more activities cannot share graphically the same beginning and ending events.
Correct Answer:

Verified
Correct Answer:
Verified
Q51: A _ is one in which the
Q52: According to Ohno and Toyota, _ is
Q53: In a PERT network, a/an _ is
Q54: When a process crosses functional boundaries, there
Q55: According to Ohno and Toyota, _ is
Q57: If learning occurs at a supplier during
Q58: Users apply _ to projects where there
Q59: [A] _ establishes the rate of improvement
Q60: The planning phase of a project is
Q61: A/An _ is a series of tasks