Multiple Choice
Positive NPV projects most often occur because:
A) analysts select sufficiently low discount rates.
B) most projects are unique and innovative.
C) cash-flow projections are extended into the future.
D) of competitive advantages held by firms.
Correct Answer:

Verified
Correct Answer:
Verified