Multiple Choice
What happens to the NPV of a one-year project if fixed costs are increased from $400 to $600, the firm is profitable, has a 15 percent tax rate and employs a 12 percent cost of capital?
A) NPV decreases by $200.00
B) NPV decreases by $173.91
C) NPV decreases by $130.00
D) NPV decreases by $151.79
Correct Answer:

Verified
Correct Answer: