Multiple Choice
Which one of the following analytical tools is not a framework that can be used to understand the context of risk?
A) PEST analysis
B) STEEP analysis
C) Scenario planning
D) SWOT analysis
E) Cause-and-effect diagram
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: It is impossible for an organisation to
Q2: Which of the following is a type
Q4: An identified and named risk; its impact;
Q5: An organisation's culture (including risk culture) and
Q6: The roles and accountabilities of an organisation's
Q7: If an organisation was willing to invest
Q8: Regular reviews of a risk management plan
Q9: Choose the best answer. Enlisting a third
Q10: Which of the following shows the correct
Q11: Working through your critical resources and value