Multiple Choice
Which of the following statements is true in relation to Gantt charts?
A) They are useful for scheduling and setting timelines.
B) They are useful for identifying and sequencing parallel and interdependent activities.
C) They are useful monitoring tools.
D) They are useful reporting tools.
E) All of these responses are correct.
Correct Answer:

Verified
Correct Answer:
Verified