Multiple Choice
Which of the following is not a characteristic of an effective stakeholder consultation and decision-making process?
A) Transparency
B) Logical process
C) Conflicting requirements always being resolved in favour of achieving the project's requirements
D) Communication being able to be understood by the stakeholders
E) Stakeholders being given a fair opportunity to express their views and concerns
Correct Answer:

Verified
Correct Answer:
Verified