Becca works as a new-product development engineer for a company that makes solar panels for residential and commercial purposes. Her company uses PERT network software for all development projects. As she nears the final month of her timeline for completing a new panel, Becca will focus on those activities that are:


A) most costly to complete.
B) on the priority bar of the PERT chart.
C) near the end of the PERT network.
D) on the critical path of the PERT network.