Multiple Choice
COGNITIVE ASSESSMENT Which of the following is a chart type, also called a network diagram, that is best suited for scheduling large, complex projects?
A) PERT
B) 3-D
C) Gantt
D) horizontal
Correct Answer:

Verified
Correct Answer:
Verified