Whereas Lump-Sum Bids Involve Calculating a Single Final Price and Assembling

Question 1

Multiple Choice

Whereas lump-sum bids involve calculating a single final price and assembling a list of subtrades, with a unit-price bid, the contractor is also required to complete a "_______", that is, an itemized breakdown of the work of the project.


A) Bid Drawing
B) Estimate File
C) Pre-bid
D) Schedule of Prices

Correct Answer:

verifed

Verified