Three Months Ago, the New Operations Manager at Acme Fastener

Question 22

Multiple Choice

Three months ago, the new operations manager at Acme Fastener and Tool's manufacturing plant implemented a system for measuring the total volume of output each week. He discovered that the plant's weekly capacity was averaging about 83%, which he would like to raise to closer to 90%. What type of metric is this manager concerned with at the moment?


A) Efficiency manufacturing
B) Quality manufacturing
C) Inventory
D) Costs and profitability