Multiple Choice
A p roject layout is:
A) a floor plan of the production facility.
B) a fixed location layout where the product remains in place for the duration of production.
C) a product-focused layout in which machines and workers are arranged according to the progressive sequence of operations.
D) a process-focused layout that groups together similar equipment or functions.
Correct Answer:

Verified
Correct Answer: