Multiple Choice
The _____ is a project management tool that illustrates the relationships among all the activities involved in completing a project and identifies the sequence of activities likely to take the longest to complete.
A) critical path method
B) Gantt chart
C) program evaluation and review technique
D) vertical integration technique
Correct Answer:

Verified
Correct Answer:
Verified