Multiple Choice
Devon Construction Co. is currently in the midst of a big residential construction project. The company's operations manager is looking at the estimated completion dates for the various phases of construction. At the site, ground excavation work takes longer than anticipated.The operations manager wishes to make up for the time lost in the other phases. However, the remaining phases are also behind schedule as the workforce is introduced to new construction techniques and raw materials. Which of the following tools can the operations manager use to better manage the project scheduling?
A) Enterprise resource planning
B) The critical path method
C) Computer-aided design
D) Vertical integration
Correct Answer:

Verified
Correct Answer:
Verified
Q39: A vehicle wheel manufacturing company headquartered in
Q40: The Baldrige National Quality Program was established
Q41: Which of the following statements is true
Q42: Discuss the role of operations management in
Q43: Which of the following is a difference
Q45: _ is an approach to production that
Q46: A(n)_ is a set of related activities
Q47: The cellular layout groups different kinds of
Q48: The only standard in the ISO 9000
Q49: The _ is a project management tool