Multiple Choice
The Flapjack Corporation had 8,200 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 1,000 units were actually produced. Labor standards were 7.6 hours per completed unit at a standard rate of $13.00 per hour.
The labor time variance is
A) $9,880 favorable
B) $9,880 unfavorable
C) $7,800 unfavorable
D) $7,800 favorable
Correct Answer: