The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: What is the amount of the fixed factory overhead volume variance?
A) $12,000 unfavorable
B) $12,000 favorable
C) $14,000 unfavorable
D) $26,000 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q13: The most effective means of presenting standard
Q48: Periodic comparisons between planned objectives and actual
Q51: Because accountants have financial expertise, they are
Q64: The total manufacturing cost variance is<br>A) the
Q77: The following data relate to direct labor
Q80: Compute the standard cost for one hat,
Q84: The Flapjack Corporation had 8,200 actual direct
Q101: Changes in technology, machinery, or production methods
Q119: Which of the following would not lend
Q147: If a company records inventory purchases at