Multiple Choice
Potential source of errors in RBI analysis regarding data quality are the following except
A) If the base line thickness were not performed the nominal thickness may be used for the original thickness
B) If original thickness not available, averaged at thickness readings may be used
C) If the original thickness not available, maximum at thickness readings may be used