Which Statement About the Directing a Project Process Is FALSE

Question 130

Multiple Choice

Which statement about the Directing a Project process is FALSE?


A) Supports the PRINCE2 principle of manage by exception
B) Is triggered by a request to initiate a project
C) Covers the day-to-day activities of the Project Manager
D) Provides a mechanism for the Project Board to assure that there is continued business justification