During the Managing a Stage Boundary Process, What Is Reviewed

Question 132

Multiple Choice

During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?


A) Benefits Review Plan
B) Product Status Account
C) Business Case
D) Project Plan

Correct Answer:

verifed

Verified