Multiple Choice
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
A) Off-specifications
B) Follow-on action recommendations
C) Issue Register
D) Risk Register
Correct Answer:

Verified
Correct Answer:
Verified