Multiple Choice
Which is a purpose of the Starting up a Project process?
A) Prevent poorly conceived projects from ever being initiated
B) Ensure the communication requirements of all stakeholders are documented
C) Learn lessons from this project
D) Document how changes required by corporate or programme management will be reviewed
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Which product describes the roles and responsibilities
Q8: Which is a purpose of the Managing
Q9: Which is the Change Authority role permitted
Q10: Which of the following statements about the
Q11: Which should be used to document any
Q13: What process provides the information required to
Q14: What is the collective name for individuals
Q15: When should the Project Board refer to
Q16: Which is NOT a true statement about