Multiple Choice
Which enables the project's products and all interdependencies to be clearly identified and documented?
A) Product breakdown structure
B) Quality Management Strategy
C) Product-based planning technique
D) Quality review technique
Correct Answer:

Verified
Correct Answer:
Verified