Multiple Choice
Which is a purpose of the Directing a Project process?
A) Create and authorize the project mandate
B) Ensure that work on products allocated to the team is authorized and agreed
C) Control the day-to-day running of the project
D) Delegate day-to-day management of the project to the Project Manager