Multiple Choice
You are not confident with the assessment of the risk level and you suspect that it will be possible to find high-priority bugs in low-risk areas. Furthermore, the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing. Which of the following answers describes the best test execution schedule in this scenario?
A) T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
B) T1, T3, T5, T7, T9, T2, T4, T6, T8, T10
C) T10, T9, T8, T7, T6, T5, T4, T3, T2, T1
D) T10, T8, T6, T4, T2, T9, T7, T5, T3, T1
Correct Answer:

Verified
Correct Answer:
Verified
Q24: After the presentation, you are asked to
Q25: Assume you are a Test Manager involved
Q26: Which of the following statements describing the
Q27: Which of the following would you expect
Q28: You are the Test Manager on a
Q30: You are the Test Manager of a
Q31: Consider an agile team adopting Extreme Programming
Q32: Assume that no additional product risks have
Q33: Assume you are working on a defect
Q34: The following is the unique "critical" quality