Assume you have some data related to confirmation testing during system testing of a past project. In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times. You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours. Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?
A) 300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure.
B) 340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of external failure.
C) 340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure.
D) 300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of detection.
Correct Answer:

Verified
Correct Answer:
Verified
Q49: Your test team consists of four members
Q50: The following are the requirements identified as
Q51: You are following a risk-based testing strategy.
Q52: In the next two months some new
Q53: For which of the following activities would
Q55: You are using this skills assessment spreadsheet
Q56: Assume you are managing a test automation
Q57: Which of the following information would you
Q58: Consider a defect report and assume that
Q59: You are performing a quality risk analysis