Multiple Choice
Consider a defect report and assume that a part of its lifecycle includes the following states: New: Is the initial state Working: Means that the developers are addressing the defect in order to produce a fix for the defect Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect Closed: is the final state Which of the following answers represents an invalid sequence of states that can't lead the bug report to the "Closed" state?
A) New, Working, Verification, Working, Clarification, Working, Verification, Closed
B) New, Working, Clarification, Working, Verification, Closed
C) New, Working, Verification, Working, Clarification, Working, Closed
D) New, Working, Verification, Closed
Correct Answer:

Verified
Correct Answer:
Verified
Q53: For which of the following activities would
Q54: Assume you have some data related to
Q55: You are using this skills assessment spreadsheet
Q56: Assume you are managing a test automation
Q57: Which of the following information would you
Q59: You are performing a quality risk analysis
Q60: Which of the following statements represents the
Q61: The following is the unique "critical" quality
Q62: You can count on well-written requirements, but
Q63: Consider the following analysis of testing skills