Multiple Choice
Which of the following inputs of Monitor and Control Risks acquires information from performance measurements and evaluates it to provide variance analysis and forecasting?
A) Risk register
B) Work performance information
C) Performance report
D) Project management plan
Correct Answer:

Verified
Correct Answer:
Verified