Several Risks Were Identified for an Upcoming Change Initiative

Question 57

Multiple Choice

Several risks were identified for an upcoming change initiative. One risk is related to a slippage concern because of loose gravel at the local site of the change initiative. The business analyst (BA) has recommended that all on-site stakeholders must wear durable, slip-resistant boots while the change initiative is being executed. This is an example of which type of risk treatment?


A) Transfer
B) Mitigate
C) Accept
D) Avoid

Correct Answer: