Multiple Choice
You are the business analyst for your organization and you're notifying the key stakeholders of a need to gather requirements for an endeavor. One of the stakeholders that you'll need to attend your requirements workshop is the project manager. What role will the project manager have in this workshop?
A) The project manager will facilitate the requirements workshop.
B) The project manager will ensure that the needed resources are available.
C) None, the project manager should not be involved until all of the requirements have been identified.
D) The project manager will help elicit requirements from the stakeholders.
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Which one of the following statements best
Q8: Which of the following describes business requirements,
Q9: You are working with the project stakeholders
Q10: A business analyst (BA) worked with two
Q11: Linda is the business analyst for her
Q13: According to the book 'A Guide to
Q14: While gathering information during a requirements workshop,
Q15: When can changes to requirements occur in
Q16: Jon is a business analyst for his
Q17: A business analyst (BA) needs approval for