Question 12

Multiple Choice

You are the business analyst for your organization and you're notifying the key stakeholders of a need to gather requirements for an endeavor. One of the stakeholders that you'll need to attend your requirements workshop is the project manager. What role will the project manager have in this workshop?


A) The project manager will facilitate the requirements workshop.  
B) The project manager will ensure that the needed resources are available.
C) None, the project manager should not be involved until all of the requirements have been identified.
D) The project manager will help elicit requirements from the stakeholders.