Multiple Choice
Project Communication Management includes the processes required to ____.
A) Ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
B) Identify, define, combine, unify, and coordinate the various processes and project management activities with the Project Management Process Groups.
C) Manage timely completion of the project.
D) Organize, manage, and lead the project team.
Correct Answer:

Verified
Correct Answer:
Verified