Multiple Choice
A company has recently incurred significant cost overruns on one of its construction projects. Management suspects that these overruns were caused by the contractor improperly accounting for costs related to contract change orders. Which of the following procedures would be appropriate for testing this suspicion?
A) Verify that the contractor has not charged change orders with costs that have already been billed to the original contract. II. Determine if the contractor has billed for original contract work that was canceled as a result of change orders. III. Verify that the change orders were properly approved by management.
B) I only
C) III only
D) I and II only
E) I and III only
Correct Answer:

Verified
Correct Answer:
Verified
Q458: Production managers for a manufacturing company are
Q459: During an audit of a contract for
Q460: Which of the following audit steps would
Q461: A code of business conduct should include
Q462: In reviewing the appropriateness of the minimum
Q463: The internal audit activity of an investment
Q465: According to the International Professional Practices Framework,
Q466: An organization's internal auditors are reviewing production
Q467: Recommendations should be included in the audit
Q468: The board has asked the internal audit