Multiple Choice
Which of the following statements is correct regarding the use of a program evaluation and review technique (PERT) model? • It makes use of a probability model to arrive at a realistic estimate of time necessary for completion of the audit engagement. • It requires that activities are performed in sequence such that each task is completed before the commencement of the next activity. • It remains fixed once completed to act as a baseline for measuring the performance of the audit staff following completion of the engagement. • It begins with the auditor-in-charge identifying the overall scope and then breaking down the audit engagement into identifiable activity units.
A) 1 and 3 only
B) 1 and 4 only
C) 2 and 3 only
D) 2 and 4 only
Correct Answer:

Verified
Correct Answer:
Verified
Q140: Which of the following is typically not
Q141: Due to the expanded role of internal
Q142: An organization has recently incurred significant cost
Q143: What would be used to determine the
Q144: Which of the following are key characteristics
Q146: According to IIA guidance, which of the
Q147: Which of the following will be an
Q148: Which of the following statements is true
Q149: According to IIA guidance, which of the
Q150: When internal auditors provide consulting services, the