Multiple Choice
An organization has recently incurred significant cost overruns on one of its construction projects. Management suspects that these overruns were caused by the contractor improperly charging for costs related to contract change orders. Which of the following procedures are appropriate for testing this suspicion? 1. Determine if the contractor has received proper approval of change orders from management. 2. Determine if the contractor has billed for original contract work cancelled by the change orders. 3. Determine if the contractor has charged change orders with costs already billed to the original contract. 4. Determine if the contractor has been paid for change orders that have not yet been completed.
A) 1 and 2 only
B) 1 and 3 only
C) 2 and 3 only
D) 3 and 4 only
Correct Answer:

Verified
Correct Answer:
Verified
Q137: During a consulting engagement, an internal auditor
Q138: Because of an abundance of high priority
Q139: Controls are implemented to:<br>A) Eliminate risk and
Q140: Which of the following is typically not
Q141: Due to the expanded role of internal
Q143: What would be used to determine the
Q144: Which of the following are key characteristics
Q145: Which of the following statements is correct
Q146: According to IIA guidance, which of the
Q147: Which of the following will be an