Question 82

Multiple Choice

An internal audit manager is supervising an engagement. A senior auditor deviates from the approved engagement plan but meets all deadlines in the approved time schedule. Which activity is not required for the audit manager to provide proper engagement supervision?


A) Actively participate in audit procedures.
B) Ensure that all engagement objectives are met.
C) Approve the deviation from the engagement plan.
D) Ensure compliance with the time schedule.