Multiple Choice
Which one of the following is the CORRECT set of steps for the continual service improvement approach?
A) Devise a strategy; Design the solution; Transition into production; Operate the solution; Continually improve
B) Where do we want to be?; How do we get there?; How do we check we arrived?; How do we keep the momentum going?
C) Identify the required business outcomes; Plan how to achieve the outcomes; Implement the plan; Check the plan has been properly implemented; Improve the solution
D) What is the vision?; Where are we now?; Where do we want to be?; How do we get there?; Did we get there?; How do we keep the momentum going?
Correct Answer:

Verified
Correct Answer:
Verified
Q232: Who is responsible for defining metrics for
Q233: Which is the BEST definition of a
Q234: Which of the following statements about processes
Q235: Which of the following should IT service
Q236: Which process includes business, service and component
Q238: Which is NOT a sub-process of capacity
Q239: Which process is responsible for recording the
Q240: What is the name given to the
Q241: Which is an example of an internal
Q242: Which service transition process provides guidance about