Multiple Choice
What is the name given to the individual assigned to carry out a risk response action or actions to respond to a particular risk or set of risks?
A) Risk Manage
B) Risk Coordinator
C) Risk Actionee
D) Risk Owner
Correct Answer:

Verified
Correct Answer:
Verified