An automotive manufacturer procures an important engine part.The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard.With respect to part quality,two primary performance metrics monitored are parts per million (PPM) defects and percent PPM improvement.The following measures are used for the scoring criteria:
Data collected on the supplied part over the present quarter indicated 15 defects with 325,000 parts received.The PPM defect rate in the prior quarter was 73.
-What is the percent improvement in the defect rate this quarter compared to the prior quarter?
A) 37%
B) 15%
C) 25%
D) 59%
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Engineering personnel are typically included as members
Q3: The table below contains a list of
Q4: Use the information below to answer the
Q5: Which is the last step in the
Q6: The first step in the supplier management
Q7: Which of the following suppliers is not
Q8: A supplier scorecard is used for price
Q9: Many firms are focused on helping their
Q10: The kind of supplier relationship that is
Q11: Use the information below to answer the