Solved

A Project Is So Large, That It Requires Multiple Scrum

Question 15

Multiple Choice

A project is so large, that it requires multiple Scrum Teams to work on it. The Scrum Teams will be working in 2 different locations. Who would lead the Sprint Planning meetings?


A) One of the Scrum Teams should lead the Sprint Planning meeting.
B) The Scrum Manager should lead the Sprint Planning meeting.
C) Each Scrum Team should lead their own Sprint Planning meeting.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions