Multiple Choice
Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.
A) Change
B) Plans
C) Progress
D) Risk
Correct Answer:

Verified
Correct Answer:
Verified