Multiple Choice
During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?
A) Project Product Description
B) Business Case
C) Project Brief
D) Project mandate
Correct Answer:

Verified
Correct Answer:
Verified