    During the Initiating a Project Process, Which Product Is Updated
Solved

During the Initiating a Project Process, Which Product Is Updated

Question 77

Question 77

Multiple Choice

During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?


A) Project Product Description
B) Business Case
C) Project Brief
D) Project mandate

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q3: Which is a purpose of the Managing

Q41: Identify the missing words in the following

Q60: Which process provides the Project Board with

Q66: Which is a responsibility of the managing

Q73: What theme provides all management levels within

Q75: Which statement is FALSE?<br>A) A project outcome

Q76: Which PRINCE2 principle helps to address a

Q80: Which describes the 'Implement' step within the

Q82: Which provides a single source of reference

Q141: Which statement defines a risk?<br>A) A certain

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines