Multiple Choice
Which provides a single source of reference that may be used by people joining a project after it has been initiated so they can quickly and easily find out how the project is being managed?
A) Project Brief
B) Project Initiation Documentation
C) Project mandate
D) Project Product Description
Correct Answer:

Verified
Correct Answer: