Question 17

Multiple Choice

An organization is assessing risks so it can prioritize its mitigation actions. Following are the risks and their probability and impact: An organization is assessing risks so it can prioritize its mitigation actions. Following are the risks and their probability and impact:   Which of the following is the order of priority for risk mitigation from highest to lowest? A)  A, B, C, D B)  A, D, B, C C)  B, C, A, D D)  C, B, D, A E)  D, A, C, B Which of the following is the order of priority for risk mitigation from highest to lowest?


A) A, B, C, D
B) A, D, B, C
C) B, C, A, D
D) C, B, D, A
E) D, A, C, B

Correct Answer: