Multiple Choice
A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
A) Project team members
B) Project sponsor
C) Project manager
D) Project scheduler
Correct Answer:

Verified
Correct Answer:
Verified