A project manager is informed that the project sponsor was terminated from the project effective immediately. To ensure business continuity, the project manager has been asked to assume additional tasks to complete the project on time. Many of these tasks were performed by the former project sponsor. Which of the following types of change does this illustrate?
A) Internal reorganization
B) Business demerger
C) Outsourcing
D) Business process change
Correct Answer:

Verified
Correct Answer:
Verified