Which of the following describes a burn rate?
A) The rate at which project documents are disposed.
B) The rate at which project personnel leave the project.
C) The rate at which the project budget is used.
D) The rate at which the timeline increases.
Correct Answer:

Verified
Correct Answer:
Verified