Multiple Choice
Which of the following is the BEST reason to conduct regular risk reviews?
A) Risk reviews ensure stakeholders take action on assigned items.
B) Risk reviews allow for the identification of response strategies.
C) Risk reviews can keep personnel on track with their assigned tasks.
D) Risk reviews must be reported in status updates.
Correct Answer:

Verified
Correct Answer:
Verified