menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Certification
  3. Study Set
    Computing Technology Industry Association (CompTIA)
  4. Exam
    Exam 11: CompTIA Project+
  5. Question
    A Milestone Task on the Critical Path Has Been Completed
Solved

A Milestone Task on the Critical Path Has Been Completed

Question 528

Question 528

Multiple Choice

A milestone task on the critical path has been completed. Which of the following should the project manager notify?


A) Owner of predecessor task
B) Project team
C) Project sponsor
D) Project steering committee

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q523: Which of the following individuals is MOST

Q524: Resources for a project report to a

Q525: When closing a project, which of the

Q526: Which of the following documents should be

Q527: A project team has purchased computers with

Q529: Based on the table below: <img src="https://d2lvgg3v3hfg70.cloudfront.net/C1257/.jpg"

Q530: The final project report should contain which

Q531: A new stakeholder has requested the status

Q532: Which of the following is the MOST

Q533: Which of the following activity sequencing techniques

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines