Multiple Choice
When closing a project, which of the following must be completed to allow team members to return to their designated departments?
A) Perform retrospective
B) Release resources
C) Obtain sign-off from the sponsor
D) Close contracts
Correct Answer:

Verified
Correct Answer:
Verified