Question 147

Multiple Choice

A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do NEXT?


A) Update the project management plan.
B) Issue a change request.
C) Revise the project charter.
D) Evaluate the impact to the baseline.